Authored by J.S. Held, this article was first published by Construction Dive in May 2025.

Introduction

The Federal Highway Administration has issued a final rule to implement the Build America, Buy America Act, which will impact transportation projects funded by federal dollars. 

While the rule may be adjusted following a regulatory freeze period, the Trump administration has expressed that it may strengthen Buy America requirements.

This final rule – issued on January 14, 2025 and went into effect on March 17, 2025 – rescinds the Manufactured Products General Waiver. Rescinding this waiver will require contractors to certify that manufactured products used on federally funded projects meet two main requirements: that final assembly of products occur in the United States, and that manufactured products be comprised of a majority of domestic content by cost.

The new rule is part of the Build America, Buy America Act, enacted in 2021 as part of the Infrastructure Investment and Jobs Act, and aims to align with federal goals of strengthening domestic supply chains and reducing reliance on foreign materials. To comply with the Buy America requirements, products must satisfy the following criteria:

  • For projects obligated on or after October 1, 2025 – Final assembly of products must occur in the United States.
  • For projects obligated on or after October 1, 2026 – Products must contain at least 55% domestic content by cost.

While these changes intend to prioritize domestic manufacturing, there may be implications for project cost, schedule, and compliance. Here’s what construction professionals need to understand about the rule, its requirements, and the potential impacts.

Potential Impacts of the Rescinded Waiver

The length of the design and construction lifecycle for projects tends to be longer in duration and typically spans different political environments. Because of this, the magnitude and timing of these changes can have various impacts, specifically if later in the project lifecycle. 

In some cases, this will lead to costly disputes from unapproved change orders, mediation, arbitration, or lengthy litigation. The rescinding of the Manufactured Products General Waiver will likely have implications to the cost, schedule, and quality of federally funded projects.

Cost:
The change in the requirements could impact project budgets due to increases in both procurement and compliance costs. This may lead to lower margins, change orders and disputes from subcontractors, the ability to bond additional projects, and financial statement pressures.

As contractors and suppliers are compelled to utilize domestic sources for manufactured products, the availability of materials – at least in the short term – is likely to be limited, leading to increased demand and rising prices. The additional requirements will also result in the need for greater resources to ensure compliance with the Buy America requirements over a broader range of products than has been needed historically.

Contractors and suppliers should consider the budget implications of these additional resources during the planning stage of the project in order to avoid later cost overruns.

Schedule:
The changes to the waiver and new requirements may also impact the entire product procurement cycle, including buyout, engineering, fabrication and delivery.

With the potential for more restrictions on product availability, the supply chain will likely entail longer-than-normal efforts to identify suitable domestic suppliers in place of foreign firms. Additional time must be allotted to vet these companies to ensure compliance with Buy America requirements and technical specifications.

Contractors should prepare up front in the planning phases with additional risk management planning and contingencies for extended procurement times or supply chain issues compared to existing product sources. A cost-benefit analysis should be considered when deciding to make a waiver request, as processing times and approvals are not guaranteed. 

Some states, such as Rhode Island, have already updated specifications to include language that any delays caused by the waiver process will be the sole responsibility of the contractor. Besides costs, contractors and suppliers would be wise to evaluate these additional time considerations associated with these processes during the development of early schedules – including pre-bid and project baselines.

Quality:
Lastly, in addition to cost and schedule concerns, contractors and suppliers must remain vigilant in ensuring product compliance with technical requirements as new vendors and new products enter the marketplace, or substandard options become available.

Contractors will want to increase quality assurance and control efforts to ensure that proper due diligence of products continues to meet the quality standards required by the contract, specifications, and industry standards.

As with cost and schedule, it would be prudent of contractors and suppliers to evaluate what additions or changes need to be made to their quality management programs to ensure that the products coming from domestic sources comply with contract requirements. Adherence to quality is not only a requirement in contracts and industry, but failures that occur because of quality issues can lead to reputational or potentially criminal issues.

Risk Mitigation at Each Project Stage

It is important to consider what steps contractors and suppliers can take and when, to remain in compliance with these requirements. Specifically, it is worthwhile to consider the pre-bid stage and the active project stage, as well as how to approach change management.

Pre-bid stage:
Contractors and suppliers should begin with a review of their existing supply chains. This review should focus on identifying potential challenges in complying with the requirements. 

Based on this evaluation, contractors and suppliers should engage as early as possible with the appropriate stakeholders to determine what steps should be taken to remain compliant. In support of this process, it may be worthwhile to perform an analysis of alternative suppliers. 

Finally, contractors and suppliers should ensure that they clearly communicate the changes in procurement requirements through their contracts and pre-bid conferences.

Active construction stage:
Communication between contractors and their suppliers will be key to ensuring compliance during the active construction stage of projects. Contractors and suppliers should be diligent in sharing information regarding costs and schedule as work progresses across the engineering, procurement and construction phases

In support of this communication, contractors and suppliers would be well-served to establish or reinforce existing tracking systems for material and implement onsite inspections to confirm compliance.

Change management:
In the event that changes are required to maintain compliance, it is essential that a protocol be established to identify, evaluate, and approve material substitutions. It is in the best interest of all stakeholders to be disciplined in maintaining documentation related to all certifications, waivers and contract modifications. 

Conclusion: Looking Ahead

The FHWA’s expansion of Buy America requirements reflects a broader commitment by the federal government to strengthening domestic manufacturing and supply chains. However, it also demands significant adjustments from project stakeholders as they consider the cost, time, and quality of projects in which they choose to engage.

The rescinding of the Manufactured Products General Waiver will likely have consequences that contractors and suppliers should begin planning for as early as possible. While the rule remains in a regulatory freeze, contractors and suppliers would do well to consider the implications on future projects. 

This includes additional focus on early and continual risk management to identify the cost, schedule, and quality impacts, and working with suppliers to understand the constraints on the supply chain. This will be critical in understanding and mitigating those impacts.

Acknowledgements

We would like to thank our colleagues Michael Peloso, PMP, PMI-SP, PMI-RMP and Dan McCrave-Bessette, PE, PSP, for providing insights and expertise that greatly assisted this research.

Michael Peloso is an Associate Director in J.S. Held’s Construction Advisory Services practice. With more than 20 years of project controls and construction claims experience, Michael provides consultant services in commercial management, project management, and scheduling for general contractors and subcontractors. Based in Boston, Michael specializes in utility, concrete, and infrastructure construction. His skills include commercial management, claims analysis, schedule development and updating, schedule delay analysis, delay & disruption damages assessment, and cost analysis.

Michael can be reached at [email protected] or +1 617 404 5326.

 

Dan McCrave-Bessette is a Director in J.S. Held’s Construction Advisory Services practice. He has nearly 15 years of experience in project management and project controls, with an emphasis on bridge, utility, concrete, and infrastructure construction. Dan utilizes his years of field experience to provide consultant services in commercial management, project management, and scheduling for general contractors, subcontractors, owners, and attorneys. Based in Boston, Dan is a professional engineer (PE) in Rhode Island and a certified planning and scheduling professional (PSP). He has provided consulting and claims analysis on complex projects, including a variety of utility, infrastructure, building, and bridge projects, both private and public.

Dan can be reached at [email protected] or +1 403 339 1013.

Find your expert.

This publication is for educational and general information purposes only. It may contain errors and is provided as is. It is not intended as specific advice, legal, or otherwise. Opinions and views are not necessarily those of J.S. Held or its affiliates and it should not be presumed that J.S. Held subscribes to any particular method, interpretation, or analysis merely because it appears in this publication. We disclaim any representation and/or warranty regarding the accuracy, timeliness, quality, or applicability of any of the contents. You should not act, or fail to act, in reliance on this publication and we disclaim all liability in respect to such actions or failure to act. We assume no responsibility for information contained in this publication and disclaim all liability and damages in respect to such information. This publication is not a substitute for competent legal advice. The content herein may be updated or otherwise modified without notice.

noun_Download_747989_000000 Created with Sketch. Download PDF
You May Also Be Interested In
Perspectives

Strategic Management of Builder’s Risk Claims in Infrastructure Projects: A Comprehensive Guide

Read real-life builder's risk claim case studies, uncover the pivotal roles of key players, & gain insights into risk management processes that safeguard project continuity and financial stability....

Perspectives

Tariffs and Trade Series: Strategies to Minimize Impacts of Tariffs on Your Construction Projects

We offer strategies to mitigate immediate and long-term effects of the fluctuating global tariff landscape on the construction industry....

Perspectives

Using Labor Productivity Analysis to Improve Budget Accuracy and Identify Inefficiencies in Emergency Mitigation Services

Understanding the benefits of labor productivity analysis in estimating, tracking, and analyzing the mitigation and remediation phase of a loss....

 
INDUSTRY INSIGHTS
Keep up with the latest research and announcements from our team.
Our Experts